Following is a list of worksheets in this appendix:
Make copies of these worksheets before continuing, so that you can complete each of the forms and keep them in a safe place for future reference in the permanent site record.
| Task | Verified by | Date |
|---|---|---|
| Date switch received | ||
| Switch and all components unpacked | ||
| Chassis components verified | ||
| Safety recommendations reviewed | ||
| Installation Checklist copied | ||
| Site Log established and background information entered | ||
| Site power voltages verified | ||
| Site environmental specifications verified | ||
| IP addresses (if needed) assigned | ||
| Required tools available | ||
| Network connection equipment available | ||
| Switch mounted in rack | ||
| Second (optional) power supply installed | ||
| AC power supplies connected to AC sources (separate lines if required) | ||
| All ejector levers checked and secure | ||
| Captive installation screws on supervisor engine module; line modules and power supplies checked | ||
| Interface cables and devices connected | ||
| ASCII1 terminal attached to the console port | ||
| Console port set for 9600 baud, 8 data bits, 2 stop bits, no parity | ||
| All power supplies turned ON | ||
| PS1 and PS2 power LEDs on for all power supplies | ||
| System boot complete (normal LEDs) | ||
| ASP2 module operational (status LED on ASP green) |
Use the Switch Component Checklist in Table A-2 to verify that all hardware and documentation items needed to complete this installation have been received before starting the installation process. Each component in the Switch Component Checklist should be verified by the person unpacking the equipment, and the list should be kept for the permanent site record.
| Component | Description | Received |
|---|---|---|
| Chassis | Switch chassis | |
| Accessory Box(es): | ||
| Power cables | One power cable for each power supply received (may be shipped separately) | |
Other optional equipment | Optional second power supply for redundant power feature | |
| Ethernet transceiver | ||
Documentation1 | Unpacking Instructions | |
| LightStream 1010 ATM Switch Hardware Installation Guide | ||
| LightStream 1010 ATM Switch ASP Installation Guide | ||
| LightStream 1010 ATM Switch PAM Installation Guide | ||
| Software license agreement | ||
| System Components: | ||
| ATM switch processor module (ASP) | Installed in slot 2 | |
| 155 UTP5 port adapter module (PAM) (unshielded twisted-pair) | Enter slot location and port addresses on the Port Configuration Worksheet | |
| 155 MM PAM (multimode fiber) | Enter slot location and port addresses on the Port Configuration Worksheet | |
| 155 SM PAM (single-mode fiber) | Enter slot location and port addresses on the Port Configuration Worksheet | |
| 155 SM/MM PAM (single-mode and multimode fiber) | Enter slot location and port addresses on the Port Configuration Worksheet | |
| 155 LR PAM (single-mode long-reach) | Enter slot location and port addresses on the Port Configuration Worksheet | |
| 1622 MM PAM (multimode fiber) | Enter slot location and port addresses on the Port Configuration Worksheet | |
| 622 SM PAM (single-mode fiber) | Enter slot location and port addresses on the Port Configuration Worksheet | |
| 622 LR PAM (single-mode long-reach) | Enter slot location and port addresses on the Port Configuration Worksheet | |
| DS-3 (Quad) PAM | Enter slot location and port addresses on the Port Configuration Worksheet | |
| DS-3 PAM | Enter slot location and port addresses on the Port Configuration Worksheet | |
| E3 PAM | Enter slot location and port addresses on the Port Configuration Worksheet | |
| T1 DSX1 PAM | Enter slot location and port addresses on the Port Configuration Worksheet | |
| E1 DSX1 PAM | Enter slot location and port addresses on the Port Configuration Worksheet | |
| E1 75-ohm PAM | Enter slot location and port addresses on the Port Configuration Worksheet | |
| CES T1 PAM | Enter slot location and port addresses on the Port Configuration Worksheet | |
| CES T1 120-PAM | Enter slot location and port addresses on the Port Configuration Worksheet | |
| CES T1 75-PAM | Enter slot location and port addresses on the Port Configuration Worksheet | |
An example LightStream 1010 ATM switch configuration is shown in Figure A-1. The example configuration includes the following elements:

| Slot | Sub. Card | PAM Type |
|---|---|---|
0 | 0 | 155 SM |
0 | 1 | 155 MM |
1 | 0 | 155 UTP |
1 | 1 | 155 UTP |
2 | - | ASP |
3 | 0 | DS-3 |
3 | 1 | E3 |
4 | 0 | 622 SM |
4 | 1 | 622 SM |
Figure A-2 displays example switch information, and Table A-3 is the completed Sample Port Configuration Worksheet for this switch.

| Slot/PAM/Port No. | PAM Type | Name |
|---|---|---|
0/0/0 | 155 SM | Bldg 1 |
0/0/1 | 155 SM | Bldg 2 |
0/0/2 | 155 SM | Bldg 3 |
0/0/3 | 155 SM | Bldg 4 |
0/1/0 | 155 MM | Floor 1 |
0/1/1 | 155 MM | Floor 2 |
0/1/2 | 155 MM | Floor 3 |
0/1/3 | 155 MM | Floor 4 |
|
|
|
1/0/0 | 155 UTP | Server 1 |
1/0/1 | 155 UTP | Server 2 |
1/0/2 | 155 UTP | Server 3 |
1/0/3 | 155 UTP | Server 4 |
1/1/0 | 155 UTP | Server 5 |
1/1/1 | 155 UTP | Server 6 |
1/1/2 | 155 UTP | Server 7 |
1/1/3 | 155 UTP | Server 8 |
Ethernet | ASP | Ethernet Port (10 Mbps) |
AUX 0 | ASP |
|
Console 0 | ASP |
|
|
|
|
3/0/0 | DS-3 | Domestic 1 |
3/0/1 | DS-3 | Domestic 2 |
3/0/2 | NA | NA |
3/0/3 | NA | NA |
3/1/0 | E-3 | Europe 1 |
3/1/1 | E-3 | Europe 2 |
3/1/2 | NA | NA |
3/1/3 | NA | NA |
|
|
|
4/0/0 | 622 SM | HS-1 |
4/0/1 | NA | NA |
4/0/2 | NA | NA |
4/0/3 | NA | NA |
4/1/0 | 622 SM | HS-2 |
4/1/1 | NA | NA |
4/1/2 | NA | NA |
4/1/3 | NA | NA |
You should fill out the blank Port Configuration Worksheet (Table A-4) before starting to configure the LightStream 1010 ATM switch.
| Slot/PAM/Port No. | PAM Type | Name |
|---|---|---|
0/0/0 |
|
|
0/0/1 |
|
|
0/0/2 |
|
|
0/0/3 |
|
|
0/1/0 |
|
|
0/1/1 |
|
|
0/1/2 |
|
|
0/1/3 |
|
|
|
|
|
1/0/0 |
|
|
1/0/1 |
|
|
1/0/2 |
|
|
1/0/3 |
|
|
1/1/0 |
|
|
1/1/1 |
|
|
1/1/2 |
|
|
1/1/3 |
|
|
|
|
|
Ethernet | ASP | Ethernet Port (10 Mbps) |
AUX 0 | ASP |
|
Console 0 | ASP |
|
|
|
|
3/0/0 |
|
|
3/0/1 |
|
|
3/0/2 |
|
|
3/0/3 |
|
|
3/1/0 |
|
|
3/1/1 |
|
|
3/1/2 |
|
|
3/1/3 |
|
|
|
|
|
4/0/0 |
|
|
4/0/1 |
|
|
4/0/2 |
|
|
4/0/3 |
|
|
4/1/0 |
|
|
4/1/1 |
|
|
4/1/2 |
|
|
4/1/3 |
|
|
Use the Site Log (Table A-5) to keep a maintenance history of the switch. A detailed description of actions performed and symptoms observed should be completed by the person performing the maintenance and kept as part of the permanent site record.
| Date | Action Performed or Symptom Observed | Initial |
|---|---|---|
The installation and configuration of the LightStream 1010 ATM switch can be separated into specific steps. If each step described in the Port Configuration Worksheet (Table A-4) is completed, switch installation should be successful. If the LightStream 1010 ATM switch fails to function properly in the first attempt, you can use the Quick Installation Worksheet to systematically check that each step was performed correctly.
Copy the Quick Installation Worksheet and initial each procedure as it is completed. Each task should be verified by the person performing the installation and dated for the permanent site record.
| Task | Completed | Date |
|---|---|---|
| Complete Switch Installation Checklist | ||
| Complete Switch Component Checklist | ||
| Complete Port Configuration Worksheets | ||
| Rack-mount the switch | ||
| Connect cables | ||
| Connect power cables | ||
| Switch power on | ||
| Configure IP address (optional) | ||
| Configure ATM address (optional) | ||
| Configure line (auxiliary or console) | ||
| Configure SNMP | ||
| Set clock (optional) | ||
| Test the configuration | ||
| Store configuration |
|
|